Jaén tram test day (2024)To proceed, feed the system actively with all the substations in the catenary. They require a series of tests where we need the tram on the route to accelerate and brake; when it accelerates, it demands more energy from the system, and when it brakes, it returns that energy to the system. During those moments, the system must operate correctly. These are the tests we are conducting. The next step is to finalize the infrastructure setup based on the results of the previous tests performed on the route. The vehicle setup is nearly complete, and the infrastructure still requires some finalization of electrical and other details. We are currently finishing the setup and preparing to begin the exploitation phase, scheduled to start in January once the contract has been awarded. At that point, we can begin testing the vehicles across the entire route, including the railway elements, etc. We are now finalizing the setup and beginning preparations for regular operation, mainly within the pre-established timeline. Yes, that part is part of the infrastructure plan. However, as it was identified later and given the high investment, it has taken some time for the contract to be awarded.
Nevertheless, it is already in place, and we will commit to it shortly. Yes, we can complete this within two to three months at most, and it will not impact the schedule. We will coordinate it with the other tasks to minimize any impact. Nothing to confirm. Clear, confirmed, and ongoing.By Diario JAÉN Reportajes -
.